NEWS
  • 18-07-2019 r.
    WWTP Tczew – close to the completion
    Construction and assembly works were completed at Czatkowy pumping station, composting plant, dense grate building, sand separator building and blowers station. At the completion is the assembly of new power and I & C installations, lighting, lightning protection.
    01-07-2019 r.
    OŚ Pińczów – The new reactor is already working
    The modernization of the first multifunctional reactor has been completed as part of the extension of the wastewater treatment plant in Pińczów. After mechanical and technological start-ups, a full volume of wastewater flowing into the treatment plant has been leaded to the reactor since the January 2019. The required values of purified wastewater rates have been achieved. The lattice building along with the sandpit has been also put into operation.
    24-06-2019 r.
    WWTP Jaworzno – works progress
    As part of the project "Modernization of the Jaworzno-Dąb II wastewater treatment plant" works related to external networks are being carried out, the renovation of the building is underway.
  • 14-06-2019 r.
    Start of modernization work at WWTP in Chrzanów Duży (Grodzisk Maz.)
    On June 14th at the headquarters of Zakład Wodociągów i Kanalizacji Sp. z o.o. in Grodzisk Mazowiecki was signed a contract for the implementation of the task: Construction of a biological reactor, reconstruction of existing biological reactors and optimization of the blowers station operation - blower replacement for the needs of the target capacity of the sewage treatment plant in Chrzanów Duży.
    10-06-2019 r.
    Moczydło Pumping station – assembly works have been completed
    The modernization works of the Moczydło sewage pump plant in Warsaw has been completed. It’s consisted of the assembly of technological, sanitary, electrical and ACPiA installations and works related to the finishing of the building.
    31-05-2019 r.
    ZUOS Tczew – stabilization hall completed
    The final acceptance protocol was signed today for the stabilization hall and the deodorization system. The commissioning of the devices took place positively and the permission for use has been obtained.
  • 21-05-2019 r.
    Sugar silo in Chełmża – assemplby of the overpass
    One of the most important completed stages of works is the assembly of a flyover at the height of 54.00 m. A crane with a lifting capacity of 750 T. was used for this purpose. Works related to the placement of these elements lasted three days.
    16-05-2019 r.
    WWTP in Dęblin – ino from the site
    As part of the investment: Reconstruction and extension of the wastewater treatment plant in Dęblin is being carried out in technological, road, finishing, construction and electrical works as well as control and measurement.
    06-05-2019 r.
    WWTP in Józefów – start up
    According to contractual requirements, the construction of the wastewater treatment plant in Józefów ended last year. Usage permit was also obtained.